A Metodologia BIM 4D e BIM 5D aplicada a um caso prático Construção de uma ETAR na Argélia

dc.contributor.advisorSilva, Francisco José Reis da
dc.contributor.advisorFaria, José Carlos Castro Pinto de
dc.contributor.authorBarbosa, Ana Cláudia Monteiro
dc.date.accessioned2015-02-04T14:40:42Z
dc.date.available2015-02-04T14:40:42Z
dc.date.issued2014
dc.descriptionMestre em Engenharia Civil – Ramo de Gestão das Construçõespor
dc.description.abstractO presente relatório inserido na Unidade Curricular de DIPRE, do Mestrado de Engenharia Civil do Instituto Superior de Engenharia do Porto, é desenvolvido no âmbito do estágio curricular na empresa EFACEC – Engenharia e Sistemas, SA, que consistiu na abordagem da metodologia Building Information Modeling (BIM) no planeamento e controlo financeiro da empreitada. Na atualidade, os Projetos são cada vez mais complexos e exigentes quanto a custos e prazos de execução. O método tradicional de gestão da construção já não consegue acompanhar esta exigência de forma eficiente. O BIM permite a mudança de mentalidades e de cooperação entre os intervenientes no setor da construção, sendo aumentada a produtividade e competitividade da equipa de Projeto. O conceito do BIM 4D surge como um avanço e melhoria na Gestão da Construção, permitindo aos profissionais da AEC simular e analisar as etapas da construção antes da sua execução. O BIM 5D tem como principal vantagem a extração de relatórios de quantidades diretamente do modelo e elaboração do orçamento baseado nessas quantidades e no tempo. No capítulo 1 deste relatório são definidos o âmbito e os objetivos deste trabalho, bem como um enquadramento geral sobre a metodologia BIM. De seguida, no capítulo 2 foi realizado um levantamento ao estado da arte sobre os temas principais que envolvem esta nova metodologia. O capítulo 3 surge como uma abordagem do método tradicional e as mudanças que o BIM oferece a toda a comunidade AEC aplicada à Gestão de Obra. E por fim, com base no projeto desenvolvido no estágio curricular, o capítulo 4 descreve toda a implementação BIM 4D e BIM 5D aplicada à construção da ETAR de Bou Ismail na Argélia.por
dc.description.abstractThis report, elaborated under the Course Unit of DIPRE which is inserted on the Master’s Degree of Civil Engineering of ISEP, was developed under the curricular internship at the company EFACEC – Engineering and Systems, SA, which aimed to do an introducing on the method of Building Information Modeling (BIM) on the management and financial control of the building construction. Currently, the projects are increasingly more complex and demanding on costs and deadlines. The traditional method of construction management can no longer go with this demand on an efficient way. BIM allows changing mentalities and cooperation between the several stakeholders construction sector, forward designated by Architecture, Engineering and Construction (AEC), increasing the productivity and competitiveness of the Project Team. The BIM 4D concept arises as a progress and improvement in Construction Management, allowing the AEC professionals to simulate and analyze the steps of the construction before its execution. The BIM 5D has the main advantage of extracting the reports amounts directly from the model and the elaboration of the budget based on the quantities and on the time duration. In chapter 1 of this report are defined the objectives and goals of this work, as well as a general framework on BIM methodology. Then, in chapter 2 was made a research to the state of the art on the main issues surrounding this new methodology. The chapter 3 appears as an approach to the traditional method and the changes that BIM offers to the entire AEC community applied to Construction Management. Finally, based on the project developed at the internship, the chapter 4 describes all the BIM 4D e BIM 5D implementation applied to the construction of Bou Ismail WWTP (Wastewater Treatment Plant) in Algeria.por
dc.identifier.tid201815842
dc.identifier.urihttp://hdl.handle.net/10400.22/5571
dc.language.isoporpor
dc.publisherInstituto Politécnico do Porto. Instituto Superior de Engenharia do Porto.por
dc.subjectAECpor
dc.subjectBIMpor
dc.subjectBIM 4Dpor
dc.subjectBIM 5Dpor
dc.subjectETARpor
dc.subjectWWTPpor
dc.titleA Metodologia BIM 4D e BIM 5D aplicada a um caso prático Construção de uma ETAR na Argéliapor
dc.typemaster thesis
dspace.entity.typePublication
rcaap.rightsopenAccesspor
rcaap.typemasterThesispor

Files

Original bundle
Now showing 1 - 1 of 1
No Thumbnail Available
Name:
DM_AnaBarbosa_2014_MEC.pdf
Size:
9.02 MB
Format:
Adobe Portable Document Format
License bundle
Now showing 1 - 1 of 1
No Thumbnail Available
Name:
license.txt
Size:
1.71 KB
Format:
Item-specific license agreed upon to submission
Description: